What This Guide Helps With

Troubleshoots frozen workstations and communication loss caused by power, cables, network connectivity, peripherals, software state, or subsystem availability.

Step-by-Step Troubleshooting

1. Protect the Patient and Preserve the Study

If the workstation freezes or loses communication during a patient examination, do not continue scanning until system status and data handling are understood.

Maintain patient safety and avoid unnecessary repeat acquisition. Do not force shutdowns that could jeopardize unsaved study data unless required for safety.

Expected outcome: The patient is safe and existing study data are protected as much as possible.

2. Define the Failure

Determine whether:

Record exact messages and visible status indicators.

Expected outcome: The issue is identified as a local workstation, scanner-communication, or broader network problem.

3. Check Workstation Power and Displays

Verify that accessible workstation and display power connections are secure.

Check:

Expected outcome: Workstation and display power are stable.

4. Check External Data and Network Connections

Inspect accessible network and communication cables.

Look for:

Do not disconnect restricted internal system network connections without service guidance.

Expected outcome: Accessible communication and network connections are secure.

5. Check Connected Peripherals

Inspect approved external peripherals for abnormal behavior.

A malfunctioning removable peripheral can sometimes coincide with workstation responsiveness problems. Disconnect or substitute only equipment that is approved for user or Clinical Engineering handling and only when doing so will not affect active patient data.

Expected outcome: No obvious external peripheral is causing or contributing to the problem.

6. Determine the Scope of the Communication Failure

Check whether other systems on the same network or imaging area are experiencing similar communication problems.

When appropriate, coordinate with IT or imaging informatics to determine whether there is a broader:

Expected outcome: A facility-network problem is identified or ruled out before the scanner is blamed.

7. Perform an Approved Workstation Restart

After protecting study data and when no patient depends on the scanner, use an approved normal shutdown and restart process.

Do not repeatedly hard-power-cycle the workstation.

Expected outcome: The workstation restarts normally, reconnects to required system components, and remains responsive.

If normal function returns, proceed to final verification.

8. Verify Complete Communication and Workflow

Confirm:

Expected outcome: The workstation and scanner communication path operate normally.

If communication remains stable and applicable functional checks pass, troubleshooting can stop and the system may be returned to service.

If the Problem Persists

If workstation power, external cabling, peripherals, network availability, and an approved restart have been verified but freezing or communication loss persists, the cause may involve workstation hardware, operating software, internal system networking, storage, subsystem communication, database services, or another service-level condition.

The system should be:

Coordinate with IT or imaging informatics when evidence points to shared infrastructure.

After repair, verify system communication, acquisition, data handling, and required network workflow before return to service.

Knowing when to stop external troubleshooting and escalate is proper troubleshooting.

Clinical Use Tip

Before restarting a frozen workstation, determine whether active or unsaved patient data could be lost and preserve the study whenever possible.

Work Order Documentation (CCR Method)

CCR = Complaint, Cause, Resolution

Complaint

What was reported by the clinical staff.

Example:
"Imaging staff reported that the Discovery MI operator workstation lost communication with the scanner during setup for a study."

Cause

What was observed during troubleshooting.

Example:
"Clinical Engineering found an accessible network connection at the workstation partially disconnected."

Resolution

What action was taken.

Example:
"Clinical Engineering reseated the connection, performed an approved workstation restart, verified stable scanner communication and data access, and completed functional checks before return to service."

Helpful Details to Include (If Known)

Final Thought

Workstation problems should be separated into local power, peripheral, scanner-communication, and network categories before internal failure is assumed. Preserve patient data, verify the complete communication path, and escalate persistent failures appropriately.

That is successful troubleshooting.